GMR synchronises 350 MW Kamalanga unit with central grid

29 Jan 2013

1

GMR group has synchronised the first unit of its 3x350 MW coal-based power project at Kamalanga, near Dhenkanal in Odisha.

This is the second coal-based power plant to be synchronised by GMR, the company said in a filing with the stock exchanges.

Work on commissioning the second and third unit of the Kamamlanga project is in progress, the release said.

The project has been implemented on multiple packages concept and is the first IPP in Odisha under MoU to have synchronised with the central grid.

The project is expected to cater to the power needs of various states, including Odisha.

Bangalore-based GMR Group is a global infrastructure major with interests in airports, energy, highways and urban infrastructure, working mostly in the public-private partnership model.

Business History Videos

History of hovercraft Part 3 | Industry study | Business History

History of hovercraft Part 3...

Today I shall talk a bit more about the military plans for ...

By Kiron Kasbekar | Presenter: Kiron Kasbekar

History of hovercraft Part 2 | Industry study | Business History

History of hovercraft Part 2...

In this episode of our history of hovercraft, we shall exam...

By Kiron Kasbekar | Presenter: Kiron Kasbekar

History of Hovercraft Part 1 | Industry study | Business History

History of Hovercraft Part 1...

If you’ve been a James Bond movie fan, you may recall seein...

By Kiron Kasbekar | Presenter: Kiron Kasbekar

History of Trams in India | Industry study | Business History

History of Trams in India | ...

The video I am presenting to you is based on a script writt...

By Aniket Gupta | Presenter: Sheetal Gaikwad

view more
View details about the software product Informachine News Trackers